Crawford RBB Progress Report
Jan 29, 2026 → Feb 14, 2026
Executive Summary
We’re processing the second tranche of 221 estimates with completion almost on track for a 3-week timeline. As of February 14, we’ve completed 100 estimates (45%) with 121 estimates projected for completion by February 21.
Recent Infrastructure Improvements:
- Week of Feb 2: Released new product management tool that dramatically speeds up our ability to vet material extractions, match them with real-world products, pull pricing data, and identify both LKQ matches and lower-carbon substitutes.
- Week of Feb 9: Onboarded 3 new HITL (Human-In-The-Loop) team members who completed training this week and are ready for full production next week.
Tranche 2 Goals
Tranche 2 Total
221 estimates
Completion Timeline
~3 weeks
Average Rate
74/week
Processing Performance
| Week Ending | Estimates | Status |
|---|---|---|
| Feb 7 | 30 | Actual |
| Feb 14 | 70 | Actual |
| Feb 21 | 121 | Projected |
Total Carbon Measured
Jan 29, 2026
56.1 t
Feb 14, 2026
46.3 t
Bypass List
| Date | Items |
|---|---|
| Jan 5 | 281 |
| Jan 29 | 302 |
| Feb 14 | 435 |
Number of exact raw line-item matches automatically extracted without AI
Top 20 Materials by CO₂e – Feb 14
| Material | Feb 14 CO₂e (t) | Jan 29 CO₂e (t) |
|---|
Processing Volume by Month
| Month | Estimates Completed |
|---|---|
| January 2026 | 128 |
| February 2026 | 167 |